Community Utilities Water Replacement Project

CY 2023 Lead Service Replacement DWSRF #12468 Sch < Click here

 

Week of September 18 – 22 Potential Road Closures < Click here
 

Week of September 11-15

 

Potential Road Closures < Click here
Week of Aug 28  

Potential Road Closures <Click Here>

 

Week of August 21 – 25  

Potential Road Closures<click here>

 

Week of August 8 – 11
Week of August 7 – August 11
  1. Langley Street (at Reading Street)
    1. Water main replacement
  2. Reading Street (Florence to Langley)
    1. Water main replacement
  3. Reading Street (Harvard to Valentine)
    1. Water main replacement
  4. Archer Street
    1. Isolated lead service replacements
  5. President Avenue (Robeson to Elsbree)
    1. Isolated sidewalk replacement
  6. Oak Grove Avenue (Bedford to Locust)
    1. Isolated sidewalk replacement
July 31 – August 4

July 24 – July 28

1.            Archer Street (Highland Avenue to dead end)

a.            Continued work from last week

2.            Reading Street (Valentine Street to Florence Street)

a.            Begin water main installation

3.            President Ave. (Robeson Street to Elsbree Streets)

a.            Continued work from last week

Lead Service Line Replacement Program for the week of 7/10/2023
Week of July 17 – July 21
  1. Archer Street (Chestnut Street to Highland Avenue)
    1. Continue/complete services, removing bypass piping, clean up and temporary restoration.
  2. Reading Street (Valentine Street to Florence Street)
    1. Begin grinding the trench for replacement of water main.
  3. Vestal and North Belmont Street
    1. Begin service hook ups to bypass piping (this work might not interfere with street closures)
  4. President Ave. (Robeson Street to Elsbree Streets)
    1. Continue granite curb and sidewalk installation.
Week of July 10th   

Week of July 10 – July 14
  1. Archer Street (Chestnut Street to Highland Ave)
    1. Replacement of Water Main, Services and temporary restoration.
  2. Reading Street (Valentine Street to Florence Street)
    1. Replacement of Water Main.
  3. Atlantic Blvd.
    1. Restoration of the street, sidewalks, granite blocks, landscape improvements.
  4. President Ave. (Robeson Street to Elsbree Streets)
    1. Granite Curb and Sidewalks installation.

 

Dates / Work

Street

Start

End

6/19 – 6/23

Lead service replacement

Potential road closures

6/19 – 6/23

Water Main Replacement

Archer Street

Eldridge Street

Highland Avenue

6/19 – 6/23

Bypass Piping Installation

North Belmont Street & Vestal Street

Hood Street

North Main Street

6/19

Sidewalk Installation

Atlantic Boulevard and side streets

N/A

N/A