CY 2023 Lead Service Replacement DWSRF #12468 Sch < Click here |
Week of September 18 – 22 | Potential Road Closures < Click here |
Week of September 11-15
|
Potential Road Closures < Click here |
Week of Aug 28 |
Potential Road Closures <Click Here>
|
Week of August 21 – 25 |
Potential Road Closures<click here>
|
Week of August 8 – 11 | ![]() |
Week of August 7 – August 11 |
|
July 31 – August 4 |
|
July 24 – July 28 |
1. Archer Street (Highland Avenue to dead end) a. Continued work from last week 2. Reading Street (Valentine Street to Florence Street) a. Begin water main installation 3. President Ave. (Robeson Street to Elsbree Streets) a. Continued work from last week |
Lead Service Line Replacement Program for the week of 7/10/2023 | ![]() |
Week of July 17 – July 21 |
|
Week of July 10th |
|
Week of July 10 – July 14 |
|
Dates / Work |
Street |
Start |
End |
6/19 – 6/23 Lead service replacement |
|
|
|
6/19 – 6/23 Water Main Replacement |
Archer Street |
Eldridge Street |
Highland Avenue |
6/19 – 6/23 Bypass Piping Installation |
North Belmont Street & Vestal Street |
Hood Street |
North Main Street |
6/19 Sidewalk Installation |
Atlantic Boulevard and side streets |
N/A |
N/A |